Obtain fire department approval
Agency: Fire Department
Before obtaining the construction permit, BuildCo needs to obtain an approval from the Fire Department.
Time and cost: 10 days, CHF 1,000
Obtain construction permit
Agency: Municipal Building Authority
The construction permit is issued by the Municipal Building Authority. The company must submit the situation plan, plans of the building and several forms to the Building Authorities.
The construction permit fee includes subsequent inspection fees involved in the construction process.
Time and cost: 120 days, CHF 20,000
Receive inspection for scaffolding works
Agency: Municipal Building Authority
The Construction Control & building inspection carries out three mandatory inspections during construction: (1) Scaffolding; (2) Excavation; (3) Frame.
Time and cost: 1 day, no charge
Receive inspection for excavation works
Agency: Municipal Building Authority
The Construction Control & building inspection carries out three mandatory inspections during construction: (1) Scaffolding; (2) Excavation; (3) Frame.
Time and cost: 1 day, no charge
Receive inspection for frame works
Agency: Municipal Building Authority
The Construction Control & building inspection carries out three mandatory inspections during construction: (1) Scaffolding; (2) Excavation; (3) Frame.
Time and cost: 1 day, no charge
Obtain approval from the department for waste and recycling
Agency: Department for waste and recycling
The waste and recycling department must clear the project stating that the project will not affect utilities infrastructure.
Time and cost: 5 days, CHF 300
Obtain approval from the department of electric power supply
Agency: Department of electric power supply
The Electricity power supply department must clear the project stating that the project will not affect utilities infrastructure.
Time and cost: 4 days. no charge
Obtain approval from the water department
Agency: Water Department
The water department must clear the project stating that the project will not affect utilities infrastructure.
Time and cost: 3 days, no charge
Obtain sewage connection from the department for waste and recycling
Agency: Department for waste and recycling
After obtaining the approval from the Department for waste and recycling, the Department of electric power supply and the Department of Water, BuildCo receives sanitary inspection and connection to water and sewerage from the Department for waste and recycling.
Time and cost: 10 days, CHF 5,000
Obtain water connection from the water department
Agency: Water Department
After obtaining the approval from the Department for waste and recycling, the Department of electric power supply and the Department of Water, BuildCo receives sanitary inspection and connection to water and sewerage from the Department for waste and recycling.
Time and cost: 5 days, CHF 2,000
Receive sanitary inspection from the department for waste and recycling
Agency: Department for waste and recycling
After obtaining the approval from the Department for waste and recycling, the Department of electric power supply and the Department of Water, BuildCo receives sanitary inspection and connection to water and sewerage from the Department for waste and recycling.
Time and cost: 1 day, no charge
Receive final inspection from the municipal building authority
Agency: Municipal Building Authority
The Municipal Building Authority conducts a final inspection to verify if the building was built according to the approved design conditions.
Time and cost: 1 day, no charge
Obtain occupancy permit from the municipal building authority
Agency: Municipal Building Authority
BuildCo applies for the occupancy permit at the Municipality by submitting the final records of the construction project.
Time and cost: 7 days, no charge