Obtain geotechnical study / soil test
Agency: Private firms
BuildCo will request a soil test for the structural calculations for the foundation.
Time and cost: 15 days, USD 1,300
Obtain Topographical / Geodetic Survey
Agency: Private Firms
Topographic Surveys are used to identify and map the contours of the land plot. Its purpose is to serve as a base map for the design of a building. It also shows the boundary lines and is used by designers to accurately show the required setbacks. It is used for the site plan, which is a mandatory requirement for all construction.
Time and cost: 5 days, USD 600
Obtain preliminary fire safety approval
Agency: Directorate General of Civil Defense, Royal Oman Police
The following documents are required:
- A copy of the surveyor’s sketch
- A copy of the title deed indicating the nature of the construction, or an approval of the site and the project from the authorities concerned
- A sketch plan of the project indicating the built area, the neighborhoods, and the heights. This plan will be reviewed to ensure that it is consistent with the safety norms. Following the initial agreement on the plan, the consultants will produce five copies of it for approval.
An initial approval will be given for implementation of the project.
Time and cost: 15 days, OMR 65
Obtain site plan approval
Agency: Ministry of Housing (MOH)
Before submitting the building application and obtaining the building permit, BuildCo must obtain the site plan approval from the Ministry of Housing (MOH).
Time and cost: 30 days, OMR 15
Obtain building permit
Agency: Muscat Municipality
BuildCo must submit the following documents along with its application for a building permit to the Engineering Affairs Section of the Muscat Municipality:
- A copy of land ownership and the original of the ownership.
- •A copy of the survey drawing
- Civil card for the individuals/ the companies commercial registration/ the authorization in the case of inheritance.
- Architectural and structural maps and structural accounts.
- Other authorities approvals according to the project.
- Soil testing report for buildings that are more than three floors.
Time and cost: 14 days, OMR 65
Obtain permit to start construction work
Agency: Muscat Municipality
After receiving the building permit, and before starting the actual work on the site, BuildCo must obtain a permit from the municipality to start the construction work.
Time and cost: 14 days, OMR 113
Request and receive inspection for foundation
Agency: Muscat Municipality
BuildCo must request the inspection from the municipality at the foundation stage.
Time and cost: 1 day, no charge
Request and receive inspection for beams
Agency: Muscat Municipality
BuildCo must submit a request to the Municipality who will conduct an inspection at the beams stage.
Time and cost: 1 day, no charge
Request and receive inspection for first roof
Agency: Muscat Municipality
BuildCo must submit a request to the Municipality, who will conduct an inspection after the first roof stage is done.
Time and cost: 1 day, no charge
Request and receive inspection for second roof
Agency: Muscat Municiaplty
BuildCo must submit a request to the Municipality, who will conduct an inspection at the second roof stage.
Time and cost: 1 day, no charge
Obtain fire safety and security approval for construction site
Agency: Directorate General of Civil Defense, Royal Oman Police
A Civil Defense team visits the site to ensure that safety requirements are satisfied and gives its final approval. In addition to the application BuildCo submits online, the following documents are required:
- A copy of the marketing certificate issued by Civil Defense to the supplier of the safety equipment installed in the building
- A copy of Civil Defense’s certificate issued to the company that carries out the installations
- A certificate or letter from any company licensed by Civil Defense to ensure that the fire equipment inside the building is tested
Time and cost: 12 days, OMR 10
Request and receive final inspection from Municipality
Agency: Muscat Municipality
In order to obtain the construction completion certificate, the Municipality has to make a final inspection and issue the completion certificate.
Time and cost: 1 day, no charge
Obtain construction completion certificate and letters for utility connections
Agency: Muscat Municipality
The supervising engineer/consultant submits a written notification to the Engineering Affairs Section of the Muscat Municipality that the building has been completed. The Engineering Affairs Section reviews the engineer’s report to check that the building complies with the building permit and conducts a final inspection. The Municipality will then issue the certificate of completion. This certificate is necessary to obtain the final utility connections.
Time and cost: 7 days, OMR 11
Request and obtain water connection
Agency: Public Authority for Electricity and Water
Public Authority for Electricity and Water will make the connections after receiving the letter for utility connections
Time and cost: 28 days, OMR 1,472
Request and obtain sewage site clearance and disposal
Agency: Oman Wastewater Company SAOC / Private companies
Oman Wastewater Company SAOC / Private companies will make the sewage connections for BuildCo.
Time and cost: 7 days, no charge