Obtain a recent proof of land ownership
Agency: Bureau de l’Enregistrement
The administration must check two items:
- That the person requesting the building permit has the right to do so. He might not necessarily be the owner of the land, but acting on behalf of the owner.
- The applicant must submit a recent list of neighboring plots. In case of inquiry they should be able to consult the neighbors.
Therefore, the cadastral extract must be recent. Although the town has access to cadastral plans, the applicant must still obtain a recent cadastral extract. It costs around 50-100 Euros and it takes a maximum of 15 days to obtain it.
Time and cost: 7 days, EUR 75
Obtain clearance from the Fire Department
Agency: Fire Department
Some municipalities request a fire department report on the owner’s behalf. The cost to obtain this report is set in the official fee schedule published in the law: December 18, 2003 Arrêté du Gouvernement de la Région de Bruxelles-Capitale fixant les redevances à percevoir en contrepartie des prestations effectuées pour des missions de prévention par le Service d’Incendie et d’Aide médicale urgente de la Région de Bruxelles-Capitale.
Time and cost: 14 days, EUR 880
Request building permit from the Municipality
Agency: Municipality
The building permit request must be filed with the Municipality along with drawings. In Brussels, an environmental impact report is not required for a warehouse construction similar to that in the Doing Business case study. Moreover, the building permit expires after 2 years from the date of issuance, if construction has not started within that period.
The Urbanism Department has 30 days to inform the applicant that the application is not complete. After that period, the administration has another 3 months, depending on the type of construction to deliver the “permis d’urbanism.” Other clearances are required such as obtaining clearance from VIVAQUA for sewage, obtaining information regarding the sewage and the depth at which the sewage pipes are located. This can take another 30 days. Contacting VIVAQUA is done by the Urbanism Department and is part of the permit request process.
Time and cost: 110 days, EUR 780
Inform Municipality of commencement of work
Agency: Municipality
The builder must inform the Municipality of the commencement of work by writing a certified letter 8 days prior to the start of construction. According to Art. 194/2 of the CoBAT, it is mandatory that the permit be posted on the construction site before the start of construction and throughout its entire duration.
Time and cost: 1 day, no charge
Receive on-site inspection from Fire Department after construction
Agency: Fire Department
Time and cost: 1 day, no charge
Inform Municipality of the completion of construction
Agency: Municipality
Time and cost: 1 day, no charge
File application and receive an inspection by the Cadastre upon completion of construction
Agency: Administration du Cadastre
Within 30 days after the warehouse is in use, BuildCo must file an application at the Cadastre for “Le Revenu Cadastral.” The request is made by completing and submitting the form. An agent will visit the building and determine its value. BuildCo does not need to be present at the inspection. They inform BuildCo of the new property tax by certified mail. The value of the property is revised on an annual basis.
Time and cost: 1 day, no charge
Apply for water and sewage connection
Agency: Hydrobru
Time and cost: 1 day, no charge
Receive inspection for water and sewage on construction site
Agency: Hydrobru
The site inspection occurs in about a week from the request (EUR 50.00 per site visit, which is paid when the connection is established, procedure 10).
Time and cost: 1 day, no charge
Obtain water and sewage connection
Agency: Hydrobru
The sewage connection is assumed to be a standard connection of high-density polyethylene, 200 millimeters (7.8 inch) by 3 meters deep.
Time and cost: 75 days, EUR 16,602